| 87 | 2 | 74 |
| 下载次数 | 被引频次 | 阅读次数 |
以平面曲线半径R=150 m、横坡i=6%、最大墩高H=91.2 m、桥长L=550 m的钢混组合梁为研究对象,通过考察现场地形地貌及临建情况,研究出在施工现场台架拼装钢主梁并浇筑桥面板形成单片组合梁结构后,再采用架桥机架设单片组合梁的施工方法,该方法可最大程度加快施工进程,满足工期要求;针对先形成单片组合梁结构再架梁的施工方法,研究配套的设计方案,采用结构简支桥面连续的结构型式设计钢混组合梁,使用MIDAS CIVIL有限元软件,特别考虑风荷载、离心力、车道偏载等,分别对施工阶段和成桥阶段的承载力、刚度、抗倾覆稳定性进行了计算分析,各项指标均满足规范要求。对于架桥机架梁喂梁、施工偏载的施工阶段进行了单独的受力分析及稳定性分析,满足规范要求。采用的设计与施工技术对于现场条件受限、顶推施工困难且桥墩较高、不具备搭设临时支墩条件进行吊装施工的小半径、高墩钢混组合梁桥提供了一定的经验及借鉴意义。
Abstract:By studying the steel-concrete composite girder bridge with plane curve radius R=150 m, transverse slope i=6%, maximum pier height H=91.2 m, and bridge length L=550 m, and investigating the topography and temporary construction of the site, the construction methods studied are as follows, after assembling the steel girder on the construction site and concreting bridge deck to form a single-piece composite beam structure, the single-piece composite beam is erected by the bridge erecting machine.This method can accelerate the construction process to the greatest extent and meet the requirements of the construction period.Aiming at the construction method of first forming single piece composite beam structure and then erecting beam, the supporting design scheme is studied, and the steel concrete composite beam is designed by using the structural type of simple supported beam.Using MIDAS CIVIL finite element software, special consideration is given to wind load, centrifugal force, lane deviation load, etc.The bearing capacity, stiffness and anti-overturning stability of construction stage and the post-construction stage are calculated and analyzed respectively.The calculation results meet the specification requirements.The stress analysis and stability analysis were carried out on the construction stage of installing girder by bridge erector and thecondition of unbalanced load during construction period, which met the requirements of the specification.The design and construction technology of the research provides some experience and reference forthe small radius and high pier steel-concrete composite girder bridge with limited on-site conditions, jacking construction is difficult, the pier is too high to set up temporary piers for hoisting construction.
[1] 胡美韵,孔祥武,朱勇锋,等.钢-UHPC轻型组合连续梁桥设计与施工[J].公路工程,2023,48(2):15-23,47.
[2] 刘曙光.钢混组合梁负弯矩区受力性能分析及优化方法研究[J].湖南交通科技,2024,50(1):87-93.
[3] 张英才,奉思东,贺君,等.波形腹板组合梁桥大节段异步浇筑施工分析[J].公路工程,2024,49(2):14-21.
[4] 韩洪举,贾健,郭吉平,等.中小跨径超宽钢板组合梁桥整孔吊装技术研究[J].公路工程,2023,48(5):52-59.
[5] 欧阳泽卉,师少辉,朱玉.狮子洋通道钢-混组合梁桥结构选型研究[J].桥梁建设,2023,53(增刊1):76-83.
[6] 吴冲.现代钢桥[M].人民交通出版社,2019:6.
[7] 杨如刚,陈正,于志兵,等.宜宾临港长江公铁大桥主桥超宽钢箱梁施工关键技术[J].桥梁建设,2024,54(1):16-22.
[8] 石雄伟,谢寅涛,杜春锦,等.变截面CSW-UHPC组合梁负弯矩区弯曲性能试验研究[J].中国公路学报,2023,36(7):193-203.
[9] 姜博,彭友松,权新蕊,等.桥面板施工顺序对钢-混组合梁桥的受力影响研究及优化[J].桥梁建设,2024,54(3):149-156.
[10] 邵旭东,应李溶君,赵旭东.型钢-UHPC组合连续梁墩顶负弯矩区接缝抗弯性能试验[J].中国公路学报,2023,36(9):34-47.
[11] 严和仲,李林辉,楚民红.复杂竖曲线宽幅组合梁桥大跨度顶推施工控制技术[J].桥梁建设,2023,53(增刊2):156-162.
[12] 李斐然,张士红,袁波.孟州黄河公路大桥组合梁整孔架设受力分析[J].桥梁建设,2021,51(2):78-84.
[13] 中华人民共和国住房和城乡建设部.钢-混凝土组合桥梁设计规范:GB 50917—2013[S].北京:中国建筑工业出版社,2014.
[14] 中交公路规划设计院有限公司.公路钢结构桥梁设计规范:JTG D64—2015[S].北京:人民交通出版社股份有限公司,2015.
[15] 中交公路规划设计院有限公司.公路钢筋混凝土及预应力混凝土桥涵设计规范:JTG 3362—2018[S].北京:人民交通出版社股份有限公司,2018.
基本信息:
DOI:10.19782/j.cnki.1674-0610.2025.01.004
中图分类号:U445.4
引用信息:
[1]杨安,梁凯,秦伟.小半径曲线高墩钢混组合梁装配化施工关键技术与设计研究[J].公路工程,2025,50(01):24-31.DOI:10.19782/j.cnki.1674-0610.2025.01.004.
基金信息:
国家重点研发计划项目(2022YFC3002600)
2024-06-19
2024
2024-09-06
2024-09-29
2024
1
2025-02-20
2025-02-20